The Naples Pier Is Past Halfway. Here's What Comes Back and What Doesn't.

Close view of a white stucco home's recessed oak entry, bronze-framed window, limestone approach and sea grape specimen.

"Barring another hurricane or bad storm." A Naples City Council member attached that condition on May 18, 2026, when reporting that the pier remains on track for a July 2027 reopening. The rebuild has storms in mind well beyond the schedule. The city describes the 18-inch piles and the higher deck as resiliency improvements. FEMA's risk guidelines, together with an earlier council decision, ruled out a permanent food stand over the water. When the pier at the west end of 12th Avenue South reopens, it will be sturdier, and simpler, than the one Ian took apart.

Halfway Through the Calendar, Past Halfway on Concrete

The City of Naples held the public groundbreaking on January 5, 2026, and construction began the next day. As of today, October 8, the project is about nine months in, and the July 2027 target is about nine months away. By that count the pier is at its midpoint.

The concrete is a little further along. The city's project page tracks these milestones:

  • December 12, 2025: FEMA obligated the project funding, clearing the way for demolition.
  • January 5–6, 2026: Groundbreaking, then the start of construction.
  • July 24, 2026: Shoreline Foundation, Inc. finished its third concrete pour, bringing the total to about 200 cubic yards. Two-thirds of the new decking had arrived.
  • September 18, 2026: Crews finished the pour at the mid-pavilion site, passing 50 percent of all the concrete the rebuild needs.

The city credits "a calm summer" for the steady pace. Demolition of the old pier is done, all test piles are in, and most production piles are in place. Crews are now building the cast-in-place concrete substructure, framing and the first sections of decking, along with electrical work and renovations to the bathroom and storage building. Installation of the ipe wood decking is planned to start after all the concrete is poured. The Naples Daily News sent a drone over the site on September 21 and published the aerial progress footage on October 1.

July 2027 is still a target. At the January groundbreaking, WINK reported that the Naples and Fort Myers Beach piers could both be finished by summer 2027 "if all goes according to plan." The May council update gave a more specific month. The 2027 hurricane season will be underway by then, and the qualifier the council member used still applies.

Every Structural Change Answers Ian

The design makes more sense once you recall what Hurricane Ian did. According to the city, about 460 feet of the pier was severely damaged on September 28, 2022. Around 140 feet ended up on the Gulf floor, including the end shelter and more than 30 pilings. The concession area, midpoint shelter and storage facilities were gutted. Only about 100 feet remained usable, and that stub reopened in November 2022. City engineers decided that most of the structural components were compromised and that the whole pier should be replaced.

The rebuild takes each weak point in turn:

Element Before Ian Rebuilt pier
Pile diameter 14 inches 18 inches
Pile layout More piles, closer together Fewer piles, spaced farther apart
Deck height Original elevation Raised overall elevation
Under the decking Original support Stronger concrete support beneath ipe decking
Food service Cosmo's at the Pier restaurant No permanent concession; a portable cart is being explored

The city says the wider pile spacing is also meant to reduce impacts on the shoreline. Ipe is a tropical hardwood chosen for its resistance to rot. Architecture and engineering are led by Turrell, Hall & Associates with Naples-based MHK Architecture, and Shoreline Foundation is the builder.

The old pier is being reused too. Council members said in May that demolition turned up unexpected material, and that old pilings have gone to a reef while larger concrete pieces were ground up for road construction.

Hurricanes have reshaped this pier before. The city counts major reconstructions after storms in 1910, 1926, 1944 and 1960, a renovation in 2015, damage from Irma two years after that, and then Ian. Gulfshore Business describes this as the seventh reconstruction of a 137-year-old structure. The current budget is about $26.3 million. Of that, Shoreline Foundation's contract accounts for $23.45 million, including a $1.17 million allowance for unforeseen conditions, and the Turrell, Hall & Associates contracts total $3,036,917.

Federal money covers about $12.66 million, including an $11,401,144.20 FEMA grant. The rest comes from state grants, $11 million in bonds, $2 million in county tourist development taxes, the city's beach fund and public donations, including contributions from Collier Community Foundation.

Why Cosmo's Isn't Coming Back

The food stand is the change people will notice most, and two decisions removed it.

Food has been sold at the pier since 1946. Cosmo's leased the restaurant space starting in 2015, selling pizza, hot dogs, drinks and beach supplies and paying the city about $100,000 a year. In July 2024, after reviewing survey results and public demand, City Council agreed by consensus that concessions were unnecessary. Members cited possible congestion at the pier entrance and noise, odors and other problems for nearby residents. FEMA then settled the question for the structure itself. It said neither the former Cosmo's restaurant nor any permanent concession stand would be allowed above water under its risk guidelines.

The council revisited food service on March 4, 2026, when it unanimously approved MHK Architecture's third design. That version cuts back the buildings on land and leaves out outdoor dining and permanent concessions. Members agreed to look into a portable cart selling water, ice cream and soda, and electrical power will be installed on the land side to support one. City Manager Gary Young told the council that FEMA would not prohibit a portable cart. He also said there was no room for a food truck, so a cart is the only mobile option. One council member asked that a cart not compete with nearby local businesses.

So far, no cart operator, solicitation or final approval has been reported. As of October 2026, the March meeting is the most recent decision on record.

To make up the lost lease revenue, the city manager pointed to an annual $500,000 Tourist Development Council grant for pier and beach-end maintenance and operations, along with beach parking revenue and beach funds.

What the Walk Out Will Look Like

The approved entry area is built around restrooms and staff space. At the March meeting, architect Maureen Minker described the plan. The north men's restroom at the entry will include a small beach patrol office with its own bathroom, plus a family restroom. A rear changing room becomes pier storage. The women's restroom on the south side gets a new shade structure with benches outside. The approved design also includes private offices and restrooms for police and beach patrol, separate from the public restrooms.

The deck itself gets one new feature, an underwater camera that lets visitors see marine life below the pier. The city's list of upcoming work includes benches and fish-cleaning stations once framing and decking are finished. Before Ian, the city says, the pier drew more than one million visitors a year to fish, socialize, watch wildlife and enjoy the Gulf. The new layout keeps all of those uses and drops the meal.

The city hasn't announced any changes to pier hours or fishing rules for the reopening. Until it does, the rules from the old pier should not be assumed to carry over.

Getting to the Sand at 12th Avenue South Until Then

While the pier is under construction, the city has closed the pier itself, its stairs, restrooms and showers, and 12th Avenue South west of Gulf Shore Boulevard South. The pier parking lot at 12th Avenue South and Gulf Shore Boulevard South is partly open. The western third is available to the public, and the eastern two-thirds is used for construction.

The closest ways onto the beach are the two pedestrian bypasses the city set up at the Broad Avenue South and 13th Avenue South beach ends. Both have restrooms, and both are scheduled to stay open for the whole project. City beach parking still runs on the usual permit-or-pay system, and the Naples Pier park page has the current lot arrangement.

The best way to follow the work between now and next summer is the city's project timeline, which adds each milestone as it happens. The next one will be the last concrete pour, which is when the ipe decking can start going down.

If you own near the 12th Avenue South beach end, or you're a remote owner deciding how the pier's return fits into your plans for 2027, Sunrizon Realty can talk through what the project timeline means for your property, with no pressure. Contact Us whenever you're ready to compare notes.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.

Work With Us

You’ve got questions and we can’t wait to answer them.

Follow Me On Instagram